Pharma Project Managemen: Delivering a WHO-GMP Ready OSD Plant in Gujarat

  • Home
  • Case Study
  • Pharma Project Managemen: Delivering a WHO-GMP Ready OSD Plant in Gujarat
WHO-GMP READY Turnkey Project
How QxP Pharma Project Consultant & GMP Services delivered a Schedule M (New) and WHO-GMP compliant formulation plant in Gujarat on a single integrated schedule, with zero major GMP observations during pre-inspection review.
Client / Facility Confidential / Leading Pharma Manufacturer (Gujarat)
Industry Sector Oral Solid Dosage (OSD) Formulation Plant
Project Location Ahmedabad, Gujarat
Project Timeline 14 Months – Detailed Engineering to Inspection Readiness
★
100% Schedule M Compliance
⏱
45 Days Ahead of Schedule
⚡
35% Rework Reduced
✓
Zero Major Mock Audit Observations
Pharma Project Managemen: Delivering a WHO-GMP Ready OSD Plant in Gujarat
!

The Operational & Technical Challenge

The client was setting up a new oral solid dosage facility in Gujarat to serve domestic and export markets. Civil, mechanical, electrical, HVAC and validation work were being handled by separate vendors with no single point of accountability. This led to three major risks: Layout and HVAC zoning conflicts that would have caused GMP gaps after construction. Delays between vendors, putting the CDSCO licensing timeline at risk. Rising costs from rework and uncoordinated procurement. The client needed an experienced pharma project management consultant who could bring every workstream under one schedule while keeping Schedule M (New) and WHO-GMP requirements built into each stage.
⚙

Our Strategic Engineering & GMP Solution

QxP took over as the single-point project management partner from detailed design stage onward. Integrated Master Schedule: We combined civil, equipment, HVAC, utilities, validation and licensing activities into one tracked plan, so validation ran in parallel with execution and not after it. GMP Design Review: We checked layouts, material and personnel flow, and cleanroom classification before construction began, so non-conformances were fixed on paper and not in concrete. Vendor and Procurement Management: We shortlisted qualified vendors, compared offers and tracked deliveries against site readiness through strategic sourcing. On-Site Supervision: Our project managers monitored construction, HVAC installation and utility integration with weekly progress reports to the client. Validation Readiness: We prepared IQ/OQ/PQ protocols and documentation in step with equipment installation. Regulatory Support: We ran a mock audit before inspection and tracked CDSCO licensing milestones.
✓

The Measured Results & Compliance Outcome

Project completed 45 days ahead of the baseline schedule. 35% fewer site rework instances, because GMP deviations were caught during design and construction. HVAC and cleanroom qualification completed in parallel, which shortened the path to certification readiness. Complete documentation handed over, audit-ready, with no major observations in the pre-inspection mock audit. Cost stayed within the approved budget through structured procurement and change control.

FAQ

How does project management help avoid GMP failures?

  • It catches layout, HVAC and documentation gaps during design and construction, before they become expensive to fix.

Why run validation in parallel with construction?

  • It shortens the time from plant completion to certification readiness.

Can QxP handle both turnkey and project management models?

  • Yes, the client chooses based on how much direct control they want.
““QxP gave us one accountable team for the entire project. Their early GMP reviews saved us from costly rework, and the documentation was inspection-ready when we needed it.””
— Sharad Thakur, VP – Projects